Como Engineers Pty. Ltd. has recently shipped the 2 tonne Modular Elution System, Carbon Regeneration and Gold Room Equipment to Al Masane Al Kobra Mining Co. for the Guyan Gold Project.
The Elution System includes a Direct Eluate Electric Heating system with full PLC control of all elution and electrowinning process steps. The plant was designed, fabricated, assembled and hot run tested in Perth, prior to disassembly and packing into 6 x 40’ sea containers all within a record-breaking 23 weeks.
The 100kg/h Electric Carbon Regeneration Kiln, modular structure, hoppers and chutes were supplied out of South Africa by our long-term partner Custom Furnaces and shipped to site in 4 x 40’ sea containers.
The entire system was manufactured to Como’s latest design with improved safety and modularity, saving significant time and cost during site installation.
The final phase of the project will be site installation and commissioning, with an expected duration of 3 weeks during which time the first gold pour will be completed.
Talk to us at Como Engineers to see how we can add value to your project. +61 (0)8 94320100 www.comoeng.com.au